Traffic Changes Coming to Restaurant Row in Salyersville

Paving operations have begun for the future westbound lanes running throughout the length of the Restaurant Row project in Salyersville. Within the next few weeks, once westbound paving is complete, the existing traffic flow will be shifted over onto the new westbound lanes, so construction can begin on the eastbound lanes. One lane of traffic travelling in each direction will remain open during this traffic change. The future eastbound lanes will undergo construction during the summer months. Closing the eastbound lanes for paving work will begin the final substantial construction phase of the Restaurant Row project. The eastbound lanes are expected to be ready for final painting in the fall.